Network Optimisation | Firmware Upgrade | National | Phase 12
Scheduled for November 18, 2025 at 9:00 PM – November 19, 2025 at 3:00 AM
Affects
Frogfoot
Under maintenance from 9:00 PM to 3:00 AM
Frogfoot FTTB
Under maintenance from 9:00 PM to 3:00 AM
Frogfoot FTTH
Under maintenance from 9:00 PM to 3:00 AM
Completed
November 19, 2025 at 3:00 AMCompleted
November 19, 2025 at 3:00 AMMaintenance has completed successfully
In progress
November 18, 2025 at 9:00 PMIn progress
November 18, 2025 at 9:00 PMMaintenance is now in progress
Planned
November 18, 2025 at 9:00 PMPlanned
November 18, 2025 at 9:00 PMProvider: Frogfoot
Maintenance Type: Standard
Maintenance Start: 2025-11-17 23:00
Maintenance End: 2025-11-18 05:00
Maintenance Description: The Core engineers must upgrade the firmware version on the core routers in Western Cape region, to version 24.4R2.