adeptict - Frogfoot Maintenance | Hardware Replacement | CPT | Matroosfontein | 15 January 2026 – Maintenance details

System Under Maintenance

Frogfoot Maintenance | Hardware Replacement | CPT | Matroosfontein | 15 January 2026

Completed
Scheduled for January 15, 2026 at 9:00 PM – January 16, 2026 at 4:00 AM

Affects

Frogfoot

Under maintenance from 9:00 PM to 4:00 AM

Frogfoot FTTH

Under maintenance from 9:00 PM to 4:00 AM

Updates
  • Completed
    January 16, 2026 at 4:00 AM
    Completed
    January 16, 2026 at 4:00 AM
    Maintenance has completed successfully
  • In progress
    January 15, 2026 at 9:00 PM
    In progress
    January 15, 2026 at 9:00 PM
    Maintenance is now in progress
  • Planned
    January 15, 2026 at 9:00 PM
    Planned
    January 15, 2026 at 9:00 PM

    Frogfoot ME engineers will replace the current switch with a new one, due to a fault on the 2nd PSU slot. 4 hours of downtime expected for customers directly connecting to Matroosfontein; the remaining customers services will be at risk during this time.